From October to December 2026, the ice rink will be closed for additional upgrades. The pickleball courts on the rink pad and adjacent basketball court will also be closed.
The City is improving the artificial ice rink at Ramsden Park with state-of-good-repair upgrades to the building’s change rooms and washrooms, as well as repairs to the rink’s refrigeration systems and dasher boards.
Project Timeline
Spring to Fall 2024: Design development
Winter 2024: Detailed design
Winter 2025: Hire a construction team
Spring 2025: Construction starts, no public access to the ice rink, change room building and basketball courts
December 2025: Construction complete, ice rink and change room building open