The City will begin construction on sections of Wellesley Street East in 2026. Work will take place between Jarvis Street and Sherbourne Street, and between Ontario Street and Parliament Street. The project includes road work, watermain replacement and streetscape improvements.

Construction is expected to take place from April to December 2026.

Construction map showing Wellesley Street East between Jarvis Street and Sherbourne Street and Wellesley Street East between Ontario Street to Parliament Street.
This map shows the sections of Wellesley Street East within the work zone.

The City will reconstruct the road, replace the watermain and the City-owned portion of substandard water services on Wellesley Street East between Jarvis Street and Sherbourne Street. The City will also resurface the road, replace the watermain and the City-owned portion of substandard water services on Wellesley Street East between Ontario Street to Parliament Street.

The project includes a number of cycling, pedestrian and accessibility improvements. These improvements include:

  • Upgraded bike lanes with poured in place curbs between the cycle track and motor vehicle lanes
  • Updated pavement markings
  • New bike traffic signal heads
  • Raised bike/bus platforms at TTC bus stops

These streetscape improvements will enhance safety, improve road conditions and extend the lifespan of the underground infrastructure.

Work Hours: Work will take place from 7 a.m. to 7 p.m., Monday to Friday, with work after hours and on weekends as required.

Water Service Disruptions: From time-to-time, the water supply to properties will be shut off to complete construction; the contractor will provide notice at least 48 hours in advance. Once you are notified about water shut off, it is recommended that you temporarily disconnect any water treatment systems (i.e. softeners or filters), water-cooled air conditioners or similar plumbing fixtures. In the event you did not receive advance notice, the City may have needed to use an emergency water shut-off to complete work.

Deliveries: The City has been working with businesses and property management representatives to accommodate delivery and loading activities during construction. If you have not yet discussed your delivery needs with the project team, please contact the staff person listed on this web page as soon as possible.

Driveway Access: The contractor will notify you of any temporary restrictions to your driveway access. If your property has two entrances, one entrance will be kept open at all times.

Accessibility Accommodation: The City’s contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction. Any temporary access disruptions will be communicated as soon as possible. If you experience a disruption, have a specific access need or related accommodation request, contact the person listed on this web page.

Stay Informed

To receive construction updates by email, please contact us and indicate that you would like to be added to the mailing list.