The Noise Bylaw provides standards for noise in Toronto. This includes decibel limits and time restrictions for some types of noise.
Noise Exemption Permits can be requested for events or activities that may be in contravention of the Noise Bylaw. Examples include:
There are five types of noise exemption permit applications:
To apply for a Noise Exemption permit a completed application form must be completed and submitted by email to the Noise Team by email to NoiseTO@toronto.ca. Forms for the five types of permit applications can be found on the City of Toronto Noise Exemptions website. Applications must be received within 28 calendar days of the start of the activity or late fees may be applied. Please note: a series of events at one location may be submitted on one application form.
After receiving an application, the City will assess it against the Noise Exemption Permit Screening Criteria to determine which level the application falls under. This level will determine the applicable fee, if supplementary documentation is required, and additional conditions that may apply to the permit.
Applicants are required to submit their permit at least four weeks in advance of the event or activity but are encouraged to submit an application as soon as preliminary event or activity details are confirmed. Depending on the permit level, applications may take three to four weeks to process, including two weeks with the City Councillor’s Office. Applicants should be aware that for Level 3 permits or more complex applications with site plans or noise mitigation plans, the Councillor’s Office may take longer than two weeks to indicate they have no objection to the application being approved.
An application for only continuous concrete pouring and large crane work does not require approval from the local City Councillor's Office(s). Instead, this type of application has been delegated to the Executive Director of ML&S or his designate.
To apply for a Noise Exemption Permit, applicants must submit the following:
After reviewing an application, the City may require:
If you are looking to submit an application in person or by regular mail, please email NoiseTO@toronto.ca or call 416-392-4380 and staff will help make arrangements.
Further information on the Noise Exemption permit, including application requirements, forms, templates and resources, how to apply, fees, and the approval process can be found by visiting the City of Toronto Noise Exemption website.
Amplified, Instrument, Construction and Other Sound
Continuous Concrete Pour: $458.00 (no tax)
Large Crane Work: $458.00 (no tax)
Late Application Fee: $85.00 (no tax)