The City is improving Goldhawk Park. The design will be determined through community engagement and is proposed to include a new basketball court and north playground.
Project Timeline
Fall 2025 to Fall 2026: Hire a design team
Winter 2027: Site investigations
Spring 2027: Design development and Community Engagement Phase 1
Summer 2027: Community Engagement Phase 2
Fall to Winter 2027: Community Engagement Phase 3 and detailed design
Spring to Summer 2028: Hire a construction team
Fall 2028: Construction starts, park closes
Late Fall 2028: Construction complete, park reopens