Project Timeline
Fall 2025 to Spring 2026: Hire a design team
Summer 2026: Site investigations
Summer to Fall 2026: Community Engagement Phase 1 and design development
Winter 2026: Community Engagement Phase 2
Spring to Summer 2027: Community Engagement Phase 3 and detailed design
Fall 2027: Hire a construction team
Spring 2028: Construction starts, park closes
Late Summer 2028: Construction complete, park reopens