The City is improving Seasons Park with a new splash pad and basketball court. The design will be shaped through community engagement.

  • Fall 2025 to Spring 2026: Hire a design team
  • Summer 2026: Site investigations
  • Fall to Winter 2026: Community Engagement Phase 1 and design development
  • Spring to Summer 2027: Community Engagement Phase 2 and detailed design
  • Fall 2027: Hire a construction team
  • Spring 2028: Construction starts, park closes
  • Fall 2028: Construction complete, park reopens

The timeline is subject to change.