Full closure of southbound DVP Off-Ramp at Richmond Street starting October 15 2025 to Spring 2026. See Travel Impacts tab below for details.
The City of Toronto is rehabilitating the following four bridges:
The scope of work for this project includes deck top rehabilitation of ID264 and ID263 and underside rehabilitation of all four bridges.
Deck top rehabilitation includes:
Underside rehabilitation includes:
The work also includes construction of a multi-use trail on the Eastern Avenue Bridge (ID264). This work will ensure that the bridges meet today’s standards and remain safe for vehicles and pedestrians into the future. The project is part of the Council-approved 2024 Capital Works Program.
Construction Update Notice 3 (Dated: September 15, 2025)
Construction Update Notice 2 (Dated: April 11, 2025)
Construction Update Notice (Dated: January 10, 2025)
Construction Notice (Dated: July 24, 2024)
Pre-Construction Notice (Dated: May 15, 2024)
Upcoming:
Stage 4 – October 2025 to Spring 2026
– Rehabilitation of northeast section of the Eastern Avenue Bridge and DVP Off-Ramp at Richmond Street Bridge including barrier wall and deck overhang replacement, expansion joint replacement, deck top concrete repairs, and replacement of asphalt and waterproofing
– Rehabilitation of substructure elements on Eastern Avenue Bridge, Richmond Street Bridge, Adelaide Street Bridge, the DVP Off-Ramp at Richmond Street
FIFA World Cup Shutdown (on top of bridges) – Spring to Summer 2026
Stage 5 – Fall to Winter 2026
– Reinstatement of centre median on Eastern Avenue Bridge
– Rehabilitation of substructure elements on Eastern Avenue Bridge, Richmond Street Bridge, Adelaide Street Bridge, the DVP Off-Ramp at Richmond Street
– Finishing and restoration activities
Current:
Stage 3 – April 2025 to October 2025
– Rehabilitation of southeast and northwest section of the Eastern Avenue Bridge including barrier wall and deck overhang replacement, expansion joint replacement, deck top concrete repairs, and replacement of asphalt and waterproofing
– Construction of multi-use trail on south side of Eastern Avenue Bridge
– Rehabilitation of substructure elements on Eastern Avenue Bridge, Richmond Street Bridge, Adelaide Street Bridge, the DVP Off-Ramp at Richmond Street
Completed:
Stage 1 – August 2024 to January 2025
– Rehabilitation of southwest section of the Eastern Avenue Bridge including barrier wall and deck overhang replacement, expansion joint replacement, deck top concrete repairs, and replacement of asphalt and waterproofing
– Rehabilitation of substructure elements on Eastern Avenue Bridge, Richmond Street Bridge, Adelaide Street Bridge, the DVP Off-Ramp at Richmond Street
Stage 2 – January 2025 to April 2025
– Rehabilitation of middle section of the Eastern Avenue Bridge including expansion joint replacement, deck top concrete repairs, and replacement of asphalt and waterproofing
– Rehabilitation of substructure elements on Eastern Avenue Bridge, Richmond Street Bridge, Adelaide Street Bridge, the DVP Off-Ramp at Richmond Street
Map showing the locations of the Eastern Avenue Bridge, Richmond Street East over King Street Bridge, Adelaide Street East over King Street Bridge, and the Don Valley Parkway Ramp over the Don River.
Schedule: Work began in July 2024 and is expected to be completed by early 2027. Please refer to Travel Impacts section for further details.
Work Hours: Work is permitted 24 hours a day, Monday to Sunday, including holidays.
Overnight Work: Some tasks, including rehabilitation of the Don Valley Parkway Ramp, will require overnight work. Timelines for overnight work will be communicated in advance. During these times, construction impacts and noise levels are expected to be similar to daytime construction activities.
Pedestrian Access: Pedestrian access will be maintained. Temporary pedestrian detours may be required.
Accessibility Accommodation: The City’s contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction. Any temporary access disruptions will be communicated as soon as possible. If you experience a disruption, have a specific access need or related request, please contact us via email or call 416-495-4214.
Parks and Trails
Map of area of Underpass Park which is closed from May 12 till Spring 2026.
Art Installations and Murals: The mirrored art piece ”Mirage”, located in Underpass Park, has been removed and safely stored. It will be reinstalled once construction has been completed.
Other existing artwork and murals on the piers may also be impacted as the work involves concrete removals, patching, and the installation of new drain pipes. StreetARToronto, who oversees these murals, will assess the damage of the murals once construction is complete and decide how to restore or replace them.
Farmers Market: The construction work will allow for the Underpass Park Farmers Market to continue to operate.
Traffic Management: Road users should expect delays and increased traffic on nearby main and side streets.
At least one lane on Eastern Avenue, Richmond Street East and Adelaide Street East will remain open in each direction.
The Don Valley Parkway Southbound Off-Ramp at Richmond Street will be fully closed from October 2025 to Spring 2026 to complete the rehabilitation work. Congestion and delays are expected. Travelers are advised to take transit if possible, leave early, and plan your route ahead of time.
Streets below the bridges including St. Lawrence Street, Lower River Street, Bayview Avenue, as well as the Don Valley Parkway – will experience periodic road impacts throughout the project. These disruptions will not all occur at the same time. All impacted roads will continue to stay open to traffic.
Multi-Use Trail: As part of the bridge rehabilitation work, the existing sidewalk on the south side of the Eastern Avenue Bridge (ID264) will be replaced with a multi-use trail. The multi-use trail will be separated from the vehicular lanes by a concrete barrier with steel railing. The City is developing plans to extend this multi-use trail west to Power Street and east to Broadview Avenue as part of future construction contracts for other area projects.
Work will be carried out in multiple stages. Vehicle lane restrictions will be in place for all stages of construction.
Traffic Restrictions – Ongoing
Monday October 6 to Thursday October 9 from 10:30 p.m. to 5:30 a.m. and Friday October 10 from 10:30 p.m. to 8:00 a.m.
Nightly Tuesday October 14 to Thursday October 16 from 10:30 p.m. to 5:30 a.m. and Friday October 17 from 10:30 p.m. to 8:00 a.m.
Tuesday October 14 from 10:30 p.m. until Spring 2026
Nightly Tuesday October 14 to Friday October 17 from 9:00 p.m. to 5:30 a.m.
Ongoing nightly lane and ramp closures expected until end of 2025. The City will continue to share schedule details closer to each closure.
Bayview Avenue – Traffic Restrictions – Week of April 7, 2025 to December 2026 (current)
Stage 3 – Traffic Restrictions – Late April 2025 to October 2025 (Current)
Eastern Avenue:
Adelaide Street:
Richmond Street:
Stage 4 – Traffic Restrictions – October 2025 to Spring 2026 (Upcoming)
Don Valley Parkway:
Eastern Avenue:
Richmond Street:
Stage 2 – Traffic Restrictions – January 15, 2025 to end of April 2025 (Complete)
Eastern Avenue:
Adelaide Street:
Stage 1 – Traffic Restrictions – August 26, 2024 to January 2025 (Complete)
Eastern Avenue:
Adelaide Street:
There will also be traffic disruptions to St. Lawrence Street and Lower River Street in 2025. Details will be provided in future webpage updates ahead of the work. The next stages of the project will be announced in future notices and webpage updates.
The City is rehabilitating the bridges and elevated roads near Eastern Avenue and Adelaide Street East. Subscribe to receive details of construction activities that may be disruptive.