The City is improving the playground in Agincourt Park as part of an ongoing program to enhance playgrounds and play spaces across the city, so that everyone can experience the joys and benefits of play for years to come.
Project Timeline
Spring 2026: Community engagement (online survey)
Summer/Fall 2026: Detailed design and hire a construction team
Fall 2026: Construction starts, playground closes
Late Fall 2026: Construction complete, playground reopens
Sign up for or unsubscribe from updates related to Agincourt Park Playground Improvements.
Level of Engagement
This project has been classified as a Consult project based on the International Association for Public Participation Spectrum. This means we collect and consider public feedback on proposed design options to inform the development of a final playground design.
Project Updates
May 2026
Online Survey
From April 17 to May 4, 2026, feedback on multiple playground design options was collected in an online survey. The survey was promoted through paid social media ads, outreach to nearby schools, the local Councillor’s office, on-site signage and on this page. The survey received a total of 261 responses.
The design team will use this feedback to refine the final playground design. The final design will be available on this page in Summer 2026.
Key Feedback Highlights
When asked to rank their playground design preference, respondents ranked Playground Design C highest (56 per cent) followed by Playground Design A (35 per cent) and Playground Design B (nine per cent).
Respondents shared that the three most important features to include in the new playground are:
senior play structure for ages five to 12
climbing structures
junior play structure for ages two to five
Respondents shared that the three least important features to include in the new playground are:
stand-up spinner toys
play panels
stand-alone toys
If budget permits, the three features respondents would like more of in the improved playground are:
climbing structures
senior play structure for ages five to 12
overhead climbing options
For seating around the playground:
79 per cent of respondents like benches
71 per cent of respondents like picnic tables
31 per cent of respondents like armour stones
The preferred colour scheme for the new playground was a mix of bright warm colours and vibrant cool colours (41 per cent) over earthy colours, like green, brown, and grey, with a pop of vibrant colours (29 per cent), and bright warm colours, like yellow, orange and red (20 percent).
Site Plan
The new proposed playground will be approximately the same size as the existing playground and will be moved closer to the main pathway to improve connectivity. It will also include enhanced features and design improvements to support accessibility.
Legend
Improved playground area with new concrete border and engineered wood fibre safety surfacing
Proposed accessible ramp with armourstone seatwalls
Proposed playground border with upright logs and decorative boulders
Proposed benches on concrete pad
Proposed concrete pad for trash and recycling bins
Reinstated and/or new concrete paving
Playground Options
All three designs:
Are AODA compliant. This means that people of varying abilities can play at the new playground
Have about the same number of play features like swings, slides, etc.
Have wood fibre safety surfacing
Design options A and C are made from metal and plastic materials, whereas option B is made from natural wood.
Playground Design A
Design A includes:
one swing set with:
two belt swings
one toddler swing
one accessible swing
one junior play structure for ages two to five with:
one double slide
one climbing option
pine stump steppers
two activity play panels
one roof
one transfer station
one senior play structure for ages five to 12 with:
one spiral slide
one climbing option
one wall climber
one crawl-through tunnel
three activity play panels including a telescope
two seats
two roofs
one transfer station
two freestanding activity play panels
two seat spinning toys
Playground Design B
Design B includes:
one swing set with:
two belt swings
one toddler swing
one accessible swing
one junior play wooden structure for ages two to five with:
one metal slide
one low post and rope climbing option
one flexible strap climbing option
one senior play wooden climbing structure for ages five to 12 with:
a log jam climbing structure with a net and lower beams
Playground Design C
Design C includes:
one swing set with:
two belt swings
one toddler swing
one accessible swing
one junior play structure for ages two to five with:
one straight slide
one wave slide
two climbing options
one wheel activity panel
two leaf roofs
one transfer station
one senior play structure for ages five to 12 with:
one curved slide
a climbing structure composed of cables and rubber straps
one seat spinning toy
one spring rider
About the Project
Agincourt Park Playground is located at the northeast end of the park.
The playground currently includes:
one swing set with:
two swings for ages two to five
two swings for ages five and up
one climbing structure with slides
a teeter-totter
a spring rider
sand under all play areas
The playground will be redesigned using community feedback and is proposed to include:
playground equipment for ages five to 12
additional seating
engineered wood fibre surfacing
an accessible pathway to the playground area
The play equipment and pathway connecting to the playground area will comply with the Accessibility for Ontarians with Disabilities Act (AODA). Learn moreĀ aboutĀ how playgrounds are made accessible.
Improvements will only be made in the general playground area and will not include any new water or lighting features or improvements to other areas of the park.