The City of Toronto will replace the watermains and water service connections to properties on both the north side and south side of King Street West from Dufferin Street to west of Close Avenue. The City of Toronto and Toronto Transit Commission will also renew the TTC tracks along King Street between Dufferin Street and Close Avenue.

Weather permitting, the construction will begin on November 23, 2026 and is anticipated to be complete in fall 2027.

This work is required to bring the watermain and streetcar track infrastructure to a state of good repair and is part of the Council-approved 2026 Capital Works Program.

There will be road restrictions as part of this project. View the Travel Impacts tab to view construction maps.

For TTC information please visit ttc.ca/KingStreetTrackRenewal.

November 2026 – Construction Update

View the construction updates for details on road restrictions in place during construction.

October 2026 – Construction Updates

View the Construction Notice for details on what to expect during construction.

The City held a virtual Public Information Meeting on November 4 to share details about the upcoming construction work. The meeting included a presentation followed by a Question and Answer period.

A copy of the presentation is available on the link below:

August 2026

Pre Construction Notice

The work area is along along King Street between Dufferin Street and Close Avenue.

In Phase 1, watermain will be replaced on the North side of King Street West.

A map highlighting north side of King Street West from Dufferin Street to Close Avenue as the work area for watermain replacement

 

In Phase 2, watermain will be replaced on the South side of King Street West.

A map highlighting south side of King Street West from Dufferin Street to Close Avenue as the work area for watermain replacement

Work Hours

Watermain work will generally take place between 7 a.m. and 7 p.m., Monday to Friday, with late work or weekend work as needed. Excavation and heavy breaking activities will occur at various times throughout the day.

TTC track replacement work will take place 24 hours a day, 7 days a week. Concrete milling and breaking activities will occur between 7 a.m. and 11 p.m. Concrete breaking is the most disruptive activity and will typically last the first one to two days of each construction phase. Around-the-clock work is required during rail installation to preserve the integrity and quality of the new rail and concrete. Overnight work may include moving new rail into position, rail installation, and rail welding or grinding.

Water Service Disruptions

From time-to-time, the water supply to properties will be shut-off to complete construction; the contractor will provide notice at least 48-hours in advance. Throughout the work, it is recommended that you temporarily disconnect any water treatment systems (i.e. softeners or filters), water-cooled air conditioners or similar plumbing fixtures. In the event you did not receive advance notice, the City may have needed to use an emergency water shut off to complete work.

Deliveries

The City will be working with businesses and property management representatives to accommodate delivery and loading activities during construction. If you have not yet discussed your delivery needs with the project team, please contact the staff person listed on this web page as soon as possible.

Accessibility Accommodation

The City’s contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction. Any temporary access disruptions will be communicated as soon as possible. If you experience a disruption, have a specific access need or related accommodation request, contact the person listed on this web page.

Preparing for construction

Effective November 1, 2026, the following route changes were introduced:

  • 504/304 King streetcars are operating as a single branch between Broadview Station and Dundas West Station.
  • 504C/304C King replacement buses are operating between Roncesvalles Avenue and Distillery (Front Street East and Cherry Street).
  • 503 Kingston Rd replacement buses were extended west to Dufferin Gate Loop.
  • 508 Lake Shore streetcars are suspended.

When construction begins, starting November 23, 2026:

  • 504/304 King streetcars will divert via Queen Street West between Shaw Street and Roncesvalles Avenue.
  • All other service changes introduced on November 1 will remain in place.

Map showing TTC Transit changes for Routes 504C and 304 C as described in text

 

Transit diversions are subject to change. Visit the TTC website for the latest TTC service details: ttc.ca/KingStreetTrackRenewal

During the watermain replacement work, starting November 23, 2026, at a minimum, one travel lane will be maintained in each direction on King Street between Dufferin Street and Close Avenue.

Following travel restrictions will be in place:

  • No access to/from local streets from King Street to Melbourne Avenue while watermain work is completed across these intersections (approximately five days)
    • North side: Cowan Avenue, Gwynne Avenue
    • South side: Dunn Avenue, Spencer Avenue, Tyndall Avenue
  • Temporary two-way access will be maintained on these streets from Queen Street and Springhurst Avenue
  • No parking or stopping on King Street through the work zone
  • TTC streetcar service on King Street will be replaced by buses
  • Temporary closures of sidewalks may be required. Pedestrian detours and signage will be in place
  • Access to businesses and properties will be maintained

Temporary closures of streets north of King Street West may be required during the watermain replacement work. Information about the closures will be updated on the project web page.

Map showing no access to/from the following local streets from King Street to Melbourne Avenue while watermain work is completed across these intersections (approximately five days)North side: Cowan Avenue, Gwynne Avenue Temporary two-way access will be maintained on these streets from Queen Street.
Phase 1 Construction Map

 

Map showing no access to/from the following local streets from King Street to Melbourne Avenue while watermain work is completed across these intersections (approximately five days)South side: Dunn Avenue, Spencer Avenue, Tyndall Avenue Temporary two-way access will be maintained on these streets from Springhurst Avenue.
Phase 2 construction map

 

 

Subscribe for Updates

The project team is working to actively keep local residents and businesses informed throughout different stages of this project. Sign up to receive construction updates by email.