The City of Toronto is planning to extend Beecroft Road north from Finch Avenue West to Drewry Avenue. This extension will replace and widen Greenview Avenue, based on the preferred solution identified in the Uptown Service Road and Associated Road Network Environmental Study Report (1993).

The project will include improved pedestrian and cycling infrastructure, along with landscaping and street trees to enhance the public realm. Construction is anticipated between 2027 and 2028.

As part of this work, the City will also close the gap in the Finch Hydro Corridor Trail between Duplex Avenue and Kenneth Avenue, improving connectivity for people walking and cycling.

The Beecroft Road Extension project includes:

  • Extending Beecroft Road, north from Finch Avenue West to Drewry Avenue
  • Completing the missing link in the Finch Hydro Corridor Trail between Duplex Avenue and Kenneth Avenue

Public consultation is an important element of this project. You will have opportunities for input at key stages throughout the detailed design phase. Information about future public consultation events will be distributed by mail and posted here.

If you have questions or comments, or would like to receive email project updates, please contact us at 416-396-4455 or subscribe to the project mailing list.

Complete: Hendon Avenue Road Safety Improvements Study
In Progress

Advance the Hendon Avenue Road Safety Improvements study.

Current: Preliminary Design & Property Acquisition
In Progress

Advance the 30 per cent Beecroft Extension Road Design study, secure property needed for the extension and complete preliminary design in preparation for the Detailed Design process.

Incomplete: Detailed Design & Public Consultation
2026-2027 – Upcoming

Detailed Design is expected to begin in 2026, followed by public and interest group consultation.

Incomplete: Utility Relocation & Construction
2027-2028 – Upcoming

Utility relocation is expected to begin in 2027, and construction is expected to begin in 2028.

  • February 6, 2024: Expropriation of Properties for the Extension of Beecroft Road – Stage 2 (2024.GG9.13)
  • June 15, 2022: Expropriation of Properties for the Extension of Beecroft Road – Stage 1 (2022.GL31.13)
  • December 16, 2020: North York Centre – REimagining Yonge (Sheppard to Finch) Municipal Class Environmental Assessment Study (2020.IE18.1)
  • July 23, 2018: Authorization to Release Section 37 Funds from Various Developments to fund the North York Service Road Extension Project (2018.MM44.47)
  • May 9, 2017: REimagining Yonge (Sheppard to Finch) Municipal Class Environmental Assessment Study – Interim Project Status Update (PW21.9)
  • June 10, 2014: North York Centre South Service Road – Environmental Assessment Addendum Study (2014.PW31.9)

Stay Informed

Sign up to receive project updates by email.