If you have any questions about the required inspections for your project, please contact your building inspector or local inspection office.
| Type of Inspection | When to Call for Inspection |
|---|---|
| Footings | at completion of formwork, before pouring concrete |
| Foundations* | at completion |
| Structural framing* | at completion including rough-in of plumbing and HVAC |
| Fire separations | at completion of wall, floor and shaft separations and fire stopping, before installing interior finishes |
| Insulation and vapour barrier | at completion of insulation & vapour barrier and before installing interior services |
| Fireplaces, gas appliances, and chimneys | at commencement of installation |
| Occupancy | consult your inspector |
| Life safety systems | at completion of standpipe, sprinkler, fire alarm and emergency lighting systems |
| Final interior inspection | at completion of interior construction |
| Final exterior inspection | at completion exterior construction |
*Construction may be done in phases. Such projects may required additional inspections.
| Type of Inspection | When to Call for Inspection |
|---|---|
| Outside storm & sanitary sewers | at completion, before back filling and ready for testing |
| Water service | at completion, before back filling and ready for testing |
| Inside storm & sanitary sewers | at completion, could be partial, ready for testing |
| Rough-in, water supply, drains, waste & vents | at completion and ready for testing |
| Occupancy | at completion of installation of all required fixtures |
| Final inspection | at completion of installation of fixtures |
| Type of Inspection | When to Call for Inspection |
|---|---|
| Rough-in HVAC**/air extraction | at completion of rough-in, before installation of insulation |
| Rough-in kitchen exhaust system (non-residential) | at completion of rough-in before operation of system |
| Occupancy | mechanical systems ready for testing |
| Final inspection | completion of all mechanical systems |
**Heating, Ventilation and Air Conditioning
Property owners are required to schedule a final inspection upon completion of their project to close the permit. Open permits may impede future real estate transactions and/or complicate future applications for building permits.