The St. Lawrence Market North Redevelopment project is taking place in three phases. The project is currently in Phase 3, construction of the new North Market Building.
On May 15, 2019, City Council approved the awarding of a contract for the construction of the new St. Lawrence Market North building at 92 Front St. to The Buttcon Limited/The Atlas Corporation Joint Venture. Construction of the new market began in July 2019. Tenants continue to customize their spaces, with a grand opening to follow on May 10, 2025. The courts are open at St. Lawrence Market North and the Farmers’ Market will move to this new location on Saturdays starting April 5, 2025.
Street occupation permits for lane closures on Front and Jarvis Streets, adjacent to the site, will be obtained by the Contractor as needed for loading purposes during construction.
Concrete trucks will be on site during construction along with a tower crane to provide handling access for materials and equipment.
There will be construction related noise and vibration while construction is taking place. Vibration may be experienced at adjacent buildings and structures.
December 2024
City staff have been transitioning to the new North Market building.
In the spring of 2025, the new court and administration offices are expected to start public operations and events for the North Market will begin.
Further details on a grand opening and farmers market programming will be communicated in the coming months.
Exterior view looking northwest from intersection of Jarvis Street and Front Street East
Open office space interior view
Interior view of atrium looking toward St. Lawrence Hall
Interior view of atrium looking toward St. Lawrence Market
Courtroom interior view
Parking garage interior view
June 2024
Work completed to date includes:
Building approaching 98 per cent completion
Mechanical and electrical systems commissioning is ongoing
Interior glazing is nearing completion
Above grade interior finishes and painting nearing completion
Millwork installation at offices and Courtrooms nearing completion
View of building exterior looking northeast from Front Street.Partial view of green roof (vegetated).Atrium view looking north to St. Lawrence Hall Building.View overlooking Market Hall, west side overhead doors and stairs to 2nd. floor.
March 2023
Work completed to date includes:
Roof installation complete
Installation of interior partitions complete at floors two through five
Mechanical and electrical systems and equipment installations nearing completion, final terminations ongoing
Interior fireproofing ongoing
Link bridge to St. Lawrence Hall ongoing
Jarvis Street streetscaping complete
Next steps:
Continue mechanical and electrical systems and final terminations
Continue installation of interior finishes and painting
Begin perimeter landscaping
Building exterior enclosure complete.Link bridge to St. Lawrence Hall.View within atrium toward feature stair and artefact display at future Farmer’s Market level.Interior view of open office with finishes to begin.
November 2022
Work completed to date includes:
Exterior curtain walls and glazing nearing completion
Roof installation nearing completion
Atrium skylight glazing complete
Installation of elevators ongoing
Installation of Interior partitions ongoing on floors 1 to 5
Mechanical and electrical systems and equipment installations are ongoing
Streetscape infrastructure along Jarvis Street nearing completion
Next steps:
Complete exterior envelope enclosure and finishes
Continue mechanical and electrical systems and equipment installations
Continue installation of interior partitions
Commence installation of interior finishes and painting
Building exterior enclosure nearing completion.Jarvis Street streetscape work nearing completion.Interior works ongoing. View within atrium, overlooking future Farmer’s Market level.Exterior view at Market Lane Park.
July 2022
Work completed to date includes:
Structural steel framing for the superstructure, including central atrium, is complete
Concrete pour completed for approximately 95 per cent of floor area
Tower crane removed
Glass curtain wall, with integrated aluminum sunshade fins, installation is approximately 80 per cent complete
Parking garage interior masonry work, along with mechanical and electrical rough-ins, is ongoing
Next steps:
Complete installation of curtain wall
Infill floors following tower crane removal
Continue mechanical and electrical rough-ins on Floors 1 to 5
Continue installation of HVAC units and elevators
Complete roof installation
Commence streetscape work along Jarvis Street
Curtain wall, with integrated aluminum sunshade fins, installation ongoing at east wing.Roof installation at west wing and main entrance ongoing.Interior of atrium with pedestrian bridges connecting east and west wings, and skylight above.Level 5 roof and skylights installation ongoing above.
March 2022
Work completed to date includes:
Structural steel framing for superstructure is nearing completion
Concrete pour completed for approximately 60 per cent of floor area
Glass curtain wall installation completed on south face (Front Street side) of west wing
Parking Level lighting fixtures have been installed and energized
Next Steps:
Glass curtain wall, with integrated aluminum sunshade fins, installation progressing on west side (Market Lane)
Framing for central atrium space progressing north
Complete pedestrian bridge connections between east and west wings
Pedestrian bridge link connection to 2nd Floor of St. Lawrence Hall underway
Commence ground level framing and glazing
Parking garage interior masonry work, along with mechanical and electrical rough-ins ongoing
Structural steel framing, including barrel vaulted roof formed by steel arches, nearing completion.Curtain wall completed on south face (Front Street) of the west wing.Framing for the five storey glass atrium space progressing north, with pedestrian bridges connecting east and west wings.Curtain wall, with integrated aluminum sunshade fins, installation ongoing at west wing.
December 2021
Work completed to date includes:
Structural steel framing for superstructure is being erected in four sequences, working from east to west, commencing from the south end of the site (Front Street) and working north towards St. Lawrence Hall
Framing from Level 2 to roof completed for sequences 2 and 3
Concrete pour completed for floor Levels 2 to 5 on west side of sequences 2 and 3
Permanent power service installation by Toronto Hydro completed
Parking Level 1 lighting fixtures have been energized
Approximately 40 per cent of superstructure faming completed to date
Next Steps:
Framing from Level 2 to roof for west side of sequence 4 ongoing
Contractor installing a temporary platform on the west side of the structure to facilitate the installation of the curtain wall
Glass curtain wall installation for sequence 2 to commence in January 2022
Parking garage interior masonry work, along with mechanical and electrical rough-ins ongoing
Approximately 40 per cent of superstructure framing completed.Installation of rebar and curtain wall anchors in progress on level 5.Concrete pour for level 5 floor slab in progress.Spray applied acoustic insulation ongoing in parking garage.
August 2021
Work completed over the summer includes:
Parking garage structure completed, including ramp to Jarvis Street. Mechanical and electrical systems rough-in work ongoing
Foundation walls waterproofing and backfill completed
Electrical room on P1 level nearing completion
Tapered concrete columns installation on Ground Floor is complete
Structural steel framing for superstructure has commenced. Progress currently at grid line 2. Approximately 15 per cent of framing completed to date
Next steps:
Structural steel frame is being erected in four sequences, working from east to west, commencing from the south end of the site (Front Street) and working north towards St. Lawrence Hall
Each sequence includes erection of steel columns and beams from Level 2 to roof, installation of steel decking, and pouring of the concrete slab on deck at each floor
Glass curtain wall installation will follow
Installation of permanent power is scheduled for mid-October 2021
Site trailers to be removed from Market Lane Park by the end of September 2021
Overview of structural steel frame construction, Sequence 1.Structural steel frame on tapered concrete columns, Ground Floor.Parking garage mechanical and electrical rough-in work ongoing.
June 2021
Work completed until the end of June 2021 includes:
Parking garage concrete structure completed
Parking garage elevator and stair cores completed
Mechanical and electrical rough-ins nearing completion
Ground floor tapered concrete columns underway (12 of 32 completed)
Ongoing work over the summer will include:
Steel superstructure construction to commence in July 2021
Glass curtain wall fabrication underway and will be installed in sequence with the steel superstructure construction
Continuation of below-grade building mechanical and electrical services
Continuing installation of elevator and stair cores above grade
Revised Timeline:
The Contractor has advised of disruptions to material and equipment supply chains due to COVID-19. This, combined with added safety protocols for workers has caused a productivity loss on-site, resulting in a delay in completion from Spring 2022 to Fall 2022.
Parking garage entry ramp to Jarvis Street ongoing.Northeast perimeter foundation walls at Parking Level 1 nearing completion.Construction of Ground Floor tapered concrete columns underway (12 of 32 completed).
April 2021
Work completed to date includes:
Perimeter waterproofing to ground floor level
Parking Level 1 perimeter foundation walls ongoing
Parking Level 1 concrete slab and interior columns
Elevator and stair cores ongoing to ground level
Electrical rough-ins ongoing
Ground Floor concrete formwork commencing
Ongoing work over the spring will include:
Completion of below grade concrete sub-structure, including foundation walls, interior columns, and ground floor level concrete slab
Continuation of below grade building mechanical and electrical services
Continuing installation of elevator and stair cores
Commencement of above grade structural construction
Parking Level 1 perimeter foundation walls ongoing, and interior columns underway.West perimeter foundation walls at Parking Level 1 ongoing.Concrete formwork for ground floor concrete slab ongoing.
January 2021
Work completed to date includes:
Perimeter waterproofing to Parking Level 1
Parking Level 2 perimeter foundation walls ongoing
Parking Level 2 concrete slab and interior columns
Parking Level 1 concrete formwork commencing
Elevator and stair cores ongoing to Parking Level 1
Electrical rough-ins ongoing
Ongoing work over the winter will include:
Continuation of below grade concrete sub-structure, including foundation walls, interior columns, and parking floor slabs
Continuing installation of elevator and stair cores
Preparations for above grade construction
Parking level 2 perimeter foundation walls ongoing, and interior columns underway. Concrete formwork for parking level 1 floor slab commencing.
West perimeter foundation walls at parking level 2 underway.
Perimeter waterproofing complete to parking level 1; commencing concrete formwork for parking level 1 floor slab.
September 2020
Work completed to date includes:
Parking Level 4 perimeter footings and foundation walls
Parking Level 4 interior columns
Commencement of elevator cores
Commencement of underground geothermal heat exchange system
Commencement of underground mechanical services
Installation of overhead sidewalk protection hoarding for above grade construction
Ongoing work over the fall will include:
Completion of underground mechanical services
Completion of below grade concrete sub-structure, including foundation walls, interior columns, and parking floor slabs
Continuing installation of elevator and stair cores
Preparations for above grade construction
Parking Level 4 perimeter foundation walls and interior columns nearing completion. Underground geothermal system ongoing.Parking Level 4 underground services nearing completion. Commencing concrete formwork for Parking Level 3 floor slab.Southeast elevator core underway.
May 2020
Work completed to date includes:
the installation of perimeter shoring along property lines
excavation work to the base of parking level 4, the final excavation depth, is nearing completion
tower crane installation for handling of materials and equipment
Ongoing work over the summer will includes:
completion of site excavated
site service connections to municipal services, i.e. power, water, sewer, and gas
construction of building footings and foundation walls including the parking garage followed by the above ground structure.
Excavation and shoring nearing completion. Tower crane installation underway.
Construction of building footings underway.
Tower crane installation complete.
February 2020
Work completed to the end of January 2020 includes:
Bulk excavation and shoring has been completed to the base of parking level 2
Connection of site water and sanitary lines to municipal network completed
Installation of insulation blankets along the perimeter of the excavation
Installation of second row of tiebacks nearing completion
Ongoing work includes:
Bulk excavation and shoring of the site
Excavation of utility service tunnel to St Lawrence Hall
Sequential excavation, tie back and lagging installation will progress through to the base of parking level 4
Following the completion of the excavation and shoring work a tower crane will be installed and construction will begin on the building foundations and parking garage followed by the above grade structure
An overview of the construction site looking north.Shoring and excavation is complete to the base of parking level 2.The installation of second row of tie backs underway.
November 2019
Work completed to the end of October includes:
Drilling and pile installation along the property line
Drilling of geothermal boreholes
Site spoils been removed and drill rigs demobilized from the site
Contractor’s field offices (trailers) have been relocated from the construction site to the adjacent Market Lane Park to facilitate site excavation
Lighting on hoarding along the park side of the site reinstated
Ongoing work includes:
Bulk excavation and shoring of the site
Sequential excavation, tie backs and lagging installation will progress from grade through to the base of parking level 4. The excavation work will require that trucks enter and exit the site primarily through the Front Street gate. Flag persons are stationed at the Front Street gate to control pedestrian and vehicle traffic during excavation and hauling activities.
Following the completion of shoring and site excavated work, construction will begin on the building foundations and parking garage, followed by the above ground structure.
Bulk excavation underway at the south east corner of North St. Lawrence Market site.Storm water cistern excavation underway at north east corner of site.Timber lagging and tie back installation along the west property line.Timber lagging and tie back installation along east and south property lines.
September 2019
Work completed over the summer months includes:
installation of sidewalk/tree protection
the removal of existing footings and sewers from previous buildings
the installation of perimeter shoring pads in preparation for shoring and excavation work
Installation of the north caisson wall
August 2019, overview showing site clearing work underway.August 2019, site clearing complete, shoring pad installation underway.September 2019, overview showing shoring piles installation underway along north and east property lines.September 2019, pile installation underway along west property line.
Next Steps
Ongoing excavation and shoring work over the fall and winter months includes:
drilling and pile installation along East, West and South property lines
sequential excavation, tie backs and lagging installation from grade through to base of Parking level 4
Following the completion of shoring and site excavated work, construction will begin on the building foundations and parking garage, followed by the above ground structure.