A new 2,600 m2 off-leash area is coming to Bob Hunter Park as part of the Parks and Recreation Facilities Master Plan! The off-leash area will be located in the northwest area of the park, along the Bob Hunter Memorial Trail, and the design will be determined with the help of community feedback.

Project Timeline

  • Spring 2023: Hire a design team
  • Summer to Fall 2023: Community engagement
  • Fall 2023 to Winter 2024: Design development
  • Winter 2024: Detailed design
  • Spring 2024: Hire a construction team
  • Summer to Fall 2024: Construction starts
  • Fall 2024: Construction complete

The timeline is subject to change.