November 13, 2021 to Fall 2023 (a substantial amount of this work was completed; however, certain elements were carried over to Stages 3, primarily on The Queensway)
Locations
The Queensway: Parkside Drive to Sunnyside Avenue
Beaty Boulevard Park: southwest corner of KQQR intersection
King Street West: KQQR Intersection to approximately 100 m south
Work Scope
Watermain replacement and sewer lining: Please refer to work details listed in Advance Work (completed)
TTC pole replacement and overhead wire installation, track work, (lighting, platforms, curbs etc.), road reconstruction (base, curb gutter, sidewalk)
Streetscape improvements at Beaty Boulevard Park
Bridge rehabilitation at The Queensway bridge at Parkside Drive (inner lanes)
Dates
September 13, 2022 to mid-March 2023 (Timelines are subject to change)
Locations
Roncesvalles Avenue: Queen Street West to Dundas Street West
Work Scope
Watermain replacement and sewer relining (west side of the street)
Queen Street West to Harvard Avenue: TTC pole replacement, overhead wire removals and installation, track work, (lighting, platforms, curbs etc.), road reconstruction (base, curb gutter, sidewalk)
Platform upgrades for accessibility on Harvard Avenue to Dundas Street West