Dates

  • Work on the Parkside Bridge has been completed with the exception of street light work, which will be scheduled within the next few months.

Location

  • Parkside Bridge at The Queensway; both underside and topside of the bridge.

Work Scope

  • Bridge rehabilitation.

Dates

  • April 5, 2021 to November 2022 (a substantial amount of this work was completed; however, certain elements were carried over to Stages 2 and 3).

Locations

  • KQQR Intersection
  • The Queensway: KQQR intersection to Parkside Drive
  • Queen Street West: KQQR Intersection to Triller Avenue
  • Roncesvalles Avenue: KQQR intersection to south of Grafton Avenue

Work Scope

  • Watermain replacement and sewer relining.
  • TTC and road work (outer lanes): Work crews will undertake the following work: TTC pole replacement, overhead wire removals and installation, track work, (lighting, platforms, curbs etc.), retaining wall installation, road reconstruction (base, curb gutter, sidewalk).

 

Dates

  • November 13, 2021 to September 13, 2022 (a substantial amount of this work was completed; however, certain elements were carried over to Stages 3, primarily on The Queensway).

Locations

  • The Queensway: Parkside Drive to Sunnyside Avenue
  • Beaty Boulevard Park: southwest corner of KQQR intersection
  • King Street West: KQQR Intersection to approximately 100 m south thereof

Work Scope

  • Watermain replacement and sewer lining: Please refer to work details listed in Advance Work (completed).
  • TTC and road work (inner lanes): Work crews will undertake the following work: TTC pole replacement and overhead wire installation, track work, (lighting, platforms, curbs etc.), road reconstruction (base, curb gutter, sidewalk).
  • Streetscape work: Work crews will undertake streetscape improvements at Beaty Boulevard Park.
  • Bridge rehabilitation: Work crews will repair The Queensway bridge at Parkside Drive (inner lanes).

Dates

  • September 13, 2022 to December 31, 2022 (Timelines are subject to change)

Locations

  • Roncesvalles Avenue: Queen Street West to Dundas Street West

Work Scope

  • Watermain replacement and sewer relining (west side of the street)
  • TTC and road work Queen Street West to Harvard Avenue: Work crews will undertake the following work: TTC pole replacement, overhead wire removals and installation, track work, (lighting, platforms, curbs etc.), road reconstruction (base, curb gutter, sidewalk).
  • Harvard Avenue to Dundas Street West: Work crews will undertake the following work: Platform upgrades for accessibility.