In 2025, the City managed approximately 850,000 tonnes of waste and disposed of approximately 392,000 tonnes of residual waste (garbage) at Green Lane Landfill (GLL), which is projected to reach capacity by 2035. Even if Toronto achieves the Province of Ontario’s target of 80 per cent waste diversion by 2050, approximately 260,000 tonnes of residual waste will still require annual management. Developing, approving and implementing a long-term residual waste management solution could take up to 10 years, making timely planning essential. Through the 2023 Council-approved Residual Waste Management Work Plan (Work Plan) (IE4.1), Solid Waste Management Services (SWMS) is evaluating feasible long-term disposal options to ensure reliable, environmentally responsible and financially sustainable residual waste management beyond GLL’s current lifespan. In the new Council term, Council will consider the findings of this work and determine the preferred long-term residual waste management strategy and the next phase of implementation.

Current Status

The Council approved Work Plan established a series of activities to evaluate the feasibility and implications of long-term residual waste management options, including:

  • landfill expansion;
  • energy-from-waste (EFW) technologies (incineration);
  • private landfill opportunities; and
  • potential facility partnerships.

The City has increased tonnages under alternate disposal contracts with three private landfills to strengthen operational contingency and provide flexibility to redirect residual waste from GLL to extend its lifespan. Current work to explore long-term residual waste management options includes technical studies, an academic-led triple bottom line evaluation, and Indigenous, stakeholder and public engagement to assess the environmental, social and economic implications of the feasible options. The findings, together with the already completed public and interested-party consultations on EFW technologies and technical feasibility assessment of GLL expansion, will inform staff recommendations to the Infrastructure and Environment Committee in Q4 2027.

Key Considerations

Residual waste management has significant environmental, financial, operational and community implications. Identifying a suitable site, obtaining regulatory approvals, and constructing new residual waste management infrastructure could take at least 10 years. Timely planning is therefore critical to maintaining long-term service continuity and reducing exposure to future disposal capacity and market risks. Input received through public engagement identified environmental impacts, public health, greenhouse gas emissions, financial and economic considerations, and energy recovery as key factors in evaluating future residual waste management options. Consultation results supported further exploration of EFW technologies, while emphasizing continued waste reduction and diversion efforts, protection of human health and the environment, and transparent decision making. Although expansion of GLL has been determined to be technically feasible, any future expansion would require an Environmental Assessment, consultation with Indigenous communities and regulatory approvals. Future Council decisions will need to balance environmental performance, financial sustainability, operational reliability, public acceptance, equity considerations and alignment with the City’s strategic goals.

Background & Context

In 2016, Council adopted the Long-term Waste Management Strategy, directing staff to maximize the lifespan of GLL through waste reduction and diversion initiatives while identifying long-term residual waste management solutions. In 2021, Council received an update (IE22.9) on amendments to Ontario’s Environmental Assessment Act requiring municipal approval for the development of new landfills, significantly constraining future landfill capacity across the province. In June 2023, Council approved the Residual Waste Management Work Plan (IE4.1), establishing a phased approach to extend the life of GLL while evaluating future residual waste management options. Since then, SWMS has implemented key milestones under the Work Plan, including expanding contingency disposal capacity through private landfill contracts, completing public and interested-party consultations on residual waste management and EFW technologies, and undertaking a technical feasibility assessment of potential GLL expansion (IE24.7). These milestones provide the foundation for the current phase of work and the development of future recommendations on the City’s preferred long-term residual waste management strategy.

Key Contact

Charlotte Ueta

Director, Policy, Planning and Outreach, Solid Waste Management Services.

Charlotte.Ueta@toronto.ca, 416-392-8506.

Atif Durrani

Project Director, Policy, Planning and Outreach, Business Transformation – Residual Waste, Solid Waste Management Services.

Atif.Durrani@toronto.ca, 416-392-5792

Additional Resources

  • Residual Waste Management
  • Update on Environmental Assessment Act Amendments Affecting Future Residual Waste Disposal Considerations (2021.IE22.9)
  • Long-Term Residual Waste Management Options for the City of Toronto (2023.IE4.1)
  • Update on the City’s Long-term Residual Waste Management Work Plan (2025.IE24.7)