The City, along with the TTC, is advancing the Scarborough East Rapid Transit (SERT) project. SERT is one of the City’s two priority transit expansion projects, alongside the Waterfront East Rapid Transit Line (WERTL).
SERT is a proposed 18.6-kilometre higher-order transit project in Scarborough, with 27 stops, and connections to TTC Line 2 and Line 5, GO Transit, the future Scarborough Subway Extension (SSE), and a potential future connection to the Line 4 Sheppard Extension.
SERT will serve key institutional destinations, including the University of Toronto Scarborough Campus (UTSC) and Centennial College, and will bring higher-order transit to eight Neighbourhood Improvement Areas. Upon completion, SERT will create more transit options in northeastern Scarborough.
SERT is at the 10 per cent design stage. Enabling work is underway to support the near-term planning and future detailed design of the SERT. Activities include geotechnical and traffic studies, environmental approvals, a high-level grade separation analysis, and a detailed assessment of environmental requirements to remediate the Morningside Landfill site for conversion into the SERT’s Maintenance and Storage Facility (MSF).
Staff are advancing this work using $10 million in City funding to develop the information required to undertake detailed design through 2028, including updated and more inclusive cost estimates. Public and stakeholder engagement will support design work for the MSF and roadway design through UTSC. Staff anticipate seeking Council authority in the second quarter of 2027 to continue advancing SERT.
While the City awaits further clarity on the Province’s intentions to extend the Line 4 Sheppard subway, the SERT project has adopted a phased approach to advancing its studies, ensuring that work south of Highway 401 can proceed.
Financial Impacts: Additional capital funding commitments will be identified through the 2027-28 budget process and regular reporting to Council.
Equity Impacts: The SERT project will serve neighbourhoods within or adjacent to eight Neighbourhood Improvement Areas.
Intergovernmental Relations: As directed by Council, staff continue to seek one-third funding commitments each from the Province and the Federal Government towards the project cost. In addition, staff are establishing two new SERT governance tables:
Council recently made key decisions to advance the SERT project:
Advancing the Next Phase of SERT: On April 22, 2026, Council adopted item EX30.11, which established SERT as one of the City’s two priority transit expansion projects, selected an MSF site, and increased the project budget by $10 million to enable advancement to the 30 per cent design stage.
Grade Separation Analysis: On February 10, 2026, Council adopted CC38.1, which directed City staff to conduct a high-level analysis of grade-separated, underground, and at-grade alternatives for the SERT project.
10 Per Cent Design Approval: On February 5, 2025, Council adopted EX20.9, which approved the 10 per cent design and endorsed SERT as a priority project for funding under the Canada Public Transit Fund.
Alignment Approval: On December 13, 2023, Council adopted EX10.17, which approved the SERT alignment and directed staff to bring the project to the 10 per cent functional design stage.
Richard Borbridge
Director, Transit Expansion
Richard.Borbridge@toronto.ca, 416-845-1857