The City is experiencing a high number of premature water meter transmission unit (MTU) failures, like other municipalities across North America. MTUs are battery-powered devices that collect and send water-use data to the City for billing. An increase in failures was first identified by City staff in winter 2023.

In May 2025, City Council approved a city-wide program to replace all 470,000 MTUs over three years (2025.IE21.2). The City contracted Neptune Technology Group (Canada) to support the MTU replacement program. The program began in April 2026 and will continue through fall 2028. Replacing the units will restore the City’s Automated Meter Reading system, providing accurate water use data, reduction in estimated bills and consistent and reliable customer service.

There is no cost to customers for MTU replacement.

The replacement program may continue to result in inquiries about replacement scheduling, estimated bills and billing adjustments.

Current Status

MTU replacements are being rolled out across nine geographic zones.

About two weeks before work starts in a new zone, City staff contact local councillors and share information on upcoming replacement activities in their ward.

Customers receive advance notice from the City when replacements will begin in their zone. They then receive follow-up communications from Neptune Technology Group on how to book an MTU replacement appointment.

Once the MTU is replaced and sending actual water-use data to the City, the customer will receive a one-time separate bill for the water used up to that date.

Customers receiving estimated water bills due to a failed MTU are encouraged to submit a manual water meter reading by contacting 311. This helps support accurate billing until the MTU is replaced.

Key Considerations

When an MTU fails, the water meter continues to record actual water use; however, the City no longer receives the water use data needed for billing. As a result, customers may be moved to estimated billing until an actual meter reading is obtained through a manual reading or MTU replacement.

Following replacement, the customer’s utility account is updated using the actual water meter reading. For accounts on estimated billing, Revenue Services issues a stand-alone bill to reconcile any difference between estimated and actual water consumption, which may result in a credit or charges. Once this is done, the account is returned to regular billing. For accounts not on estimated billing, Revenue Services issues a stand-alone bill based on actual consumption up to the date of MTU replacement.

Customers can call 311 and select Option 1, Monday to Friday from 8:30 a.m. to 6 p.m., to reach a customer care team dedicated to assisting with bill adjustment or the submission of manual meter readings.

Background & Context

MTUs were installed with City water meters between 2009 and 2015. The MTUs were designed with batteries expected to last 20 years. In winter 2023, City staff identified an increase in premature MTU failures. Analysis and engagement with the manufacturer and supplier confirmed that the failures were related to the MTU batteries.

In July 2024, the City entered into a non-competitive emergency contract with Aclara Technologies LLC to secure an initial supply of replacement MTUs.

In November 2024, Council adopted IE17.2, authorizing Toronto Water to negotiate with Aclara Technologies LLC for additional replacement MTUs and approving interim procurement authorities to maintain a reliable supply of MTUs while a longer term replacement strategy was developed.

In May 2025, Council adopted IE21.2, approving the replacement of all 470,000 MTUs across Toronto over a three-year period.

The City subsequently executed contracts with Aclara Technologies LLC to supply replacement MTUs and related field programming tools, and with Neptune Technology Group Canada to complete installation. The city-wide replacement program began in April 2026 and is expected to be completed in fall 2028.

Key Contact

Lisa Botticella

Manager, MTU Replacement Program, Toronto Water

Lisa.Botticella@toronto.ca, 416-676-8917

Daniel Galluzzo

Manager, Billing & Customer Service, Revenue Services

Daniel.Galluzzo@toronto.ca, 416-395-1053

Additional Resources

Date modified: November 15, 2026