Project Timeline

  • July 2021: Hire a design team
  • November-December 2021: Community engagement
  • Winter 2022-Spring 2022: Design development
  • Early Summer 2022: Contract award
  • Spring 2024: Park Completion

The timeline is subject to change.

As part of a new mixed-use development at 6 Lloyd Ave., there will be a new 868m2 municipal park. The park will be located at the northeast corner of Mulock Avenue and Lloyd Avenue, directly across from Keele-Mulock Parkette. The property developer will be leading the construction of the new park and will be preparing two concept design options for community feedback. The new park may include:

  • A plaza space with seating and shade
  • An outdoor fitness area with ping pong and games tables
  • New plantings

The City will be leading the community engagement for this project. The park concept is being developed in consultation with the community.

Sign Up Now

Sign up for updates related to the new park at 6 Lloyd Avenue or unsubscribe from the mailing list.