Environmental Assessment Timeline

Phase Progress Events

Phase 1

Winter 2018

Problem and Opportunity Statement

Phase 2

Spring 2018 – Fall 2019

Spring 2018 – Fall 2018: 

Background Data Collection and Analysis

Fall 2018 – Spring 2019: 

Long List of Alternatives and Evaluation Criteria

Spring 2019 – Fall 2019: 

Evaluate Alternatives to Select Short List and Preferred Solution

Spring 2019: Public Event #1

Summer 2019: Report to Council

Fall 2019: Public Event #2

Phase 3

Winter 2020 – Spring 2020

Alternative Design Concepts for Preferred Solution Spring 2020: Public Event #3

Phase 4

Summer 2020

Final EA Report (30 day review period) Report to Council

Phase 5

Future

Project Implementation

 

Map of the Study Area

The map shows the study area, and phase 1 and 2 of the project. The Study area is where data collection and analysis is being completed. This is bound by Roxborough St W, Mt Pleasant / Jarvis, King St, and University Avenue. In the Phase 1 focus area, it is the area which alternative solutions are currently being developed and evaluated. This is bound by Carlton St / College St, Church St, Queen St, and Bay St. The Phase 2 future focus area will be an EA to develop and evaluate design solutions for Yonge from College to Davenport and will commence upon completion of the yongeTOmorrow phase 1. Wider Neigbourhood Impacts: YongeTOmorrow will consider the existing conditions and impacts of the alternatives on the north-south and east-west streets within the study area before making a final recommendation for the focus area.
Boundaries of the Study Area are Roxborough St W, Mt Pleasant / Jarvis, King St, and University Avenue. Boundaries of Phase 1 are Carlton St / College St, Church St, Queen St, and Bay St. Boundaries of Phase 2 are Davenport, College St, Church St and Bay St.