This page describes City of Toronto construction projects happening between Yonge to the DVP and Davenport to the Lake.

Start Date

November 24, 2019

Planned End Date

August 2020

Location

Jarvis Street, from Queen Street East to Front Street East

Description Of Work

The City of Toronto will replace the watermain and the City-owned portion of substandard water services on Jarvis Street from Queen Street East to Front Street East and resurface the road from Queen Street East to Richmond Street East.

Construction Notice

Start Date

May 11, 2020

Planned End Date

June 30, 2020

Location

Church Street and Queen Street East Intersection

Description of Work

The City of Toronto will replace the watermain at the intersection of Church Street. Following watermain commissioning City and TTC Crews will replace the streetcar track and roadway in the intersection, from early June to June 30 the intersection will be fully closed.

Construction Notice – May 1, 2020

Construction Update – May 21, 2020

Start Date

January 2019

Planned End Date

Early 2021

Location

Jarvis Street to Cherry Street

For more information please see the FG Gardiner Expressway Rehabilitation project web page.

While we aim to provide fully accessible content, there is no text alternative available for some of the content on this page. If you require alternate formats or need assistance understanding our maps, drawings, or any other content, please contact us at 416-392-3074 or downtownconstructionprojects@toronto.ca.