This page describes City of Toronto construction projects happening between Yonge Street to the Don Valley Parkway and Davenport Road to the Lake.

Start Date

January 2019

Planned End Date

Spring 2021

Location

Jarvis Street to Cherry Street

For more information please see the FG Gardiner Expressway Rehabilitation project web page.

Start Date

Spring 2021

Planned End Date

Fall 2021

Location

Queen’s Quay to the Esplanade

Description of Work

The City of Toronto will replace the watermain and the City-owned portion of substandard water services on Lower Jarvis Street from the Queen’s Quay to the Esplanade and the sanitary sewer from south of Lakeshore Boulevard East to north of the Metrolinx Bridge.

Pre-Construction Notice

Start Date

Spring 2022

Planned End Date

Summer 2022

Location

Yonge Street to Church Street

Description of Work

The City of Toronto and Toronto Transit Commission are renewing aging streetcar tracks on Wellington Street from Yonge Street to Church Street. Track renewal will also be undertaken on Church Street south of King Street East to Wellington Street. In addition to the TTC track work this project will include streetscape improvements at the intersection of Wellington Street and Church Street.

Construction Notice

Construction Update 1

Construction Update 2

Construction Update 3


Wellington Track Replacement & Streetscape  Improvements – Project Delays

As announced in the last Construction Update, the City has halted construction work until spring 2022 due to the discovery of underground conflicts. The City will be working closely with affected utilities to address and resolve the challenges ahead of restarting construction. For more information about project delays please see our Project Notes July 2, 2021.

 

September Project Update 2021

Please see the linked copy of the report by City staff on the Wellington Street Capital Projects.
A copy of the staff report is also available at Agenda Item History – 2021.IE24.14 (toronto.ca).

The report responds to City Council’s direction to report back to the Infrastructure and Environment Committee at its September 14th meeting, regarding the work on Wellington Street East.  The report identifies the outstanding work to complete, including a timeline and potential options to accelerate outstanding work ahead of June 2022. This report will be received for information at the Committee’s meeting on September 14.

Members of the public can arrange to speak or submit comments to the Committee.

If you want to speak at the meeting, you must contact the Infrastructure and Environment Committee Administrator at 416-397-4592 or iec@toronto.ca by 4:30 p.m. on September 13, 2021.

You can also submit comments by emailing the Committee at iec@toronto.ca. Communications and public submissions will become part of the public record and will be listed in the legislative record of the meeting.

Start Date

June 21, 2021

Planned End Date

November 2022

Location

Dundas Street East to Bloor Street East

Description of Work

The City of Toronto plans to replace the watermain and the City-owned portion of substandard water services on Jarvis Street from Dundas Street East to Bloor Street East, including Ted Rogers Way.

Pre Construction Notice
Construction Notice
Construction Update 1

While we aim to provide fully accessible content, there is no text alternative available for some of the content on this page. If you require alternate formats or need assistance understanding our maps, drawings, or any other content, please contact us at 416-392-3074 or downtownconstructionprojects@toronto.ca.