Construction scheduling and traffic updates for the project can be found here.
Tasks | Schedule |
---|---|
Widen Harbour Street to four lanes along with streetscape improvements | July – January 2018 |
Y-B-Y ramp opening | January 29, 2018 |
Streetscaping improvements and installation of multi-use trail | September 7, 2018 |
Asphalt paving and permanent road markings | September 12, 2018 – September 16, 2018
**Timeline is subject to change and heavily weather dependent. |
Planting streetscape elements | Late September to early October |
Construction to complete the remaining road and streetscaping work on Harbour Street continues. By September 7, 2018 the contractor will have completed:
The grinding and removal of old asphalt and installation of top course asphalt paving and permanent road markings will be completed from 9 p.m. Wednesday, September 12 to 11 p.m. Sunday, September 16. In order to complete this work, overnight road work and intersection closures are required.
For detailed information, please view the Construction Update below:
Previous Construction Updates: