Tasks Schedule
Widen Harbour Street to four lanes along with streetscape improvements July – January 2018
Y-B-Y ramp opening January 29, 2018
Streetscaping improvements and installation of multi-use trail September 7, 2018
Asphalt paving and permanent road markings September 12, 2018 – September 16, 2018

**Timeline is subject to change and heavily weather dependent.

Planting streetscape elements Late September to early October

 

Update: September 2018

Construction to complete the remaining road and streetscaping work on Harbour Street continues. By September 7, 2018 the contractor will have completed:

  • installing the new multi-use trail on the south side of Harbour Street between Lower Simcoe Street and Bay Street
  • installing permanent traffic control signal heads (lights), and permanent pavement markings
  • installing new curb and brick gutter on the north side of Harbour Street, between York Street to Bay Street, and permanent sidewalks where required

The grinding and removal of old asphalt and installation of top course asphalt paving and permanent road markings will be completed from 9 p.m. Wednesday, September 12 to 11 p.m. Sunday, September 16. In order to complete this work, overnight road work and intersection closures are required.