In May 2022, the Liberty Village Construction Hub was launched to conduct logistical planning of the right-of-way, review Construction Management Plans, connect travellers with real-time information, collaborate with enforcement officers and communicate impacts and changes to businesses and communities in the neighbourhood.
Project | Location | Dates |
---|---|---|
TTC track and watermain replacement | King Street, from Dufferin Street to Shaw Street | February to December 2024 |
Gardiner Expressway Strategic Rehabilitation – Section 2 | Dufferin street to Strachan Avenue | Until 2027 |
Road resurfacing | Ossington Avenue, from Argyle Street to Foxley Street | May 2024 to May 2025 |
TTC track replacement | Fleet Street and Bathurst Street | August to November 2024 |
Watermain replacement | Bathurst Street, from Fleet Street to Lake Shore Boulevard | August to November 2024 |