The City completed the Eglinton Park Master Plan in 2019 and is working towards park improvements in a phased approach based on the four priority areas identified in the Master Plan and the available project budget. A three-phase community engagement process for Phase 1 Implementation: Priority Area 1 of the Master Plan is currently taking place.

While we aim to provide fully accessible content, there is no text alternative available for some of the content on this site. If you require alternate formats or need assistance understanding the following content, please contact Tonya Crawford at 416-338-3171.

Sign Up for Updates

Sign Up Now

Sign up for updates related to the Eglinton Park Master Plan or unsubscribe from the list.

Level of Engagement

This project has been classified as a Collaborate project based on the International Association of Public Participation Spectrum. This means we aim to partner with the public, stakeholders and rightsholders in each aspect of the design process, including the development of design options and the identification of a preferred design.

This section is organized as follows:

  • Timeline
  • Priority Area 1 improvements
  • Project Updates

Timeline

  • Winter 2021: Hire a design team
  • Fall 2022 to Winter 2023/2024: Community engagement
  • Spring to Winter 2024: Design development
  • Spring 2024: Hire a construction team
  • Fall 2024: Construction starts
  • Spring 2025: Construction complete

The timeline is subject to change.

The City is currently implementing improvements to Priority Area 1, which will only include general park upgrades, including:

  • North/south pathway from the North Toronto Community Centre to Roselawn Avenue
  • Dogs off-leash area
  • Skateboard stop (small skateboarding area)
  • Historic themed gardens
  • Improvements to the existing stairs at Oriole Parkway

Project Updates

All updates related to the community engagement process are available in the Community Engagement Phase 1, 2, and 3 sections on this page.

February 2024

The community engagement process continues and is anticipated to be completed before spring 2024.

March 2023

Master Plan Revisions

Revisions are made to the 2019 Master Plan to incorporate feedback collected during Community Engagement Phase 1. Visit the Eglinton Park Master Plan section to see the revisions.

April 2022

Phase 1 Implementation Starts

The project team starts the process of implementing Phase 1, Priority Area 1 of the Master Plan.

March 2022

Consultant Hired

On March 28, 2022, a consultant is hired to assist in the development and implementation of the Master Plan.

November 2021

Call for Landscape Architect Consultant

On November 22, 2021, a request for a landscape architect consultant is released.

This phase of the community engagement process for Phase 1 Implementation: Priority Area 1 started in September 2022 and included:

  • A pop-up event at Eglinton Park
  • An online interactive mapping activity
  • Meetings with a Community Advisory Group (CAG) and an Indigenous and Gardening Advisory Group (IGAG)

As an outcome of this phase, the project team through conversations with members of the community and the CAG have introduced a new location option in the park for the skate spot that would better integrate with existing park programming and amenities. More information about the draft design options can be found in the reports in this section.

January 2023

Indigenous and Gardening Advisory Group 1

On January 10, 2023, the project team met with the IGAG.

Download the:

December 2022

Community Advisory Group Meeting 1

On December 6, 2022, the project team met with the CAG. Subsequent meetings occurred with particular groups as part of the CAG based on conversations shared during the first meeting.

Download the:

October 2022

Interactive Mapping Activity (Social Pinpoint)

From October 4 to October 21, 2022, an online interactive mapping activity using Social Pinpoint was available for community members to share their thoughts on the proposed design and learn about the upcoming changes that will be delivered as part of Phase 1 of the Master Plan implementation.

Park Pop-Up Events

On October 2 and 3, an event took place along the pathway that connects the North Toronto Soccer Club Centre and Tommy Flynn Playground. The project team shared information about the implementation of the Master Plan and a design exercise was available to gain insights on the preferred locations and options for the off-leash area and skate spot. The final locations for the off-leash area and skate spot will be determined using the feedback from the pop-up events, consultation with the Community Advisory Group, Indigenous Groups and City staff.

Download the summary report for the Social Pinpoint and Park Pop-Up.

Off-Leash Area

There are two proposed locations for an off-leash area, which will be approximately 2,000m2.

Image illustrates the two proposed locations for the dog off-leash area (OLA). From the bottom left to top right. Location A – in the centre of the park at the bottom of the existing hill, west of the Arena Location B - in the centre of the park and west of the parking lot.

Skate Spot

There are three proposed locations for a skate spot, which will be approximately 600m in size and include one to three skate features. A fourth location, not represented in the map below, was identified by City staff in response to the CAG’s concern that having the OLA and the skate spot centrally located in the park would result in a loss of green space and size of recreation fields. The fourth skate spot location is the green space in front of the North Toronto Memorial Community Centre entrance on Eglinton Avenue West, adjacent to the outdoor swimming pool. This location was shared with the CAG in an online survey, where it was identified as being the preferred location. This location is accessible and visible from the street and will complement the future basketball court identified in the Master Plan.

Image illustrates the three proposed locations for the skate spot. From the bottom left to top right. Location A – at the southwest corner of the park Location B – in the centre of the park at the bottom of the existing hill, west of the Arena Location C - in the centre of the park and west of the parking lot.

August 2022

Indigenous Consultant Hired

The City is partnering with Ridge Road Training and consulting on the Eglinton Park Master Plan Implementation, to facilitate an Indigenous-centred engagement process. The process is grassroots, flexible, and rooted in relationship building. It will adapt as we learn more from those who we speak and share space with. Those who are invited to participate in this engagement process will be provided an honorarium as compensation for their valuable knowledge, time, and any additional contributions they make towards the process.

The City and Ridge Road will be engaging with groups such as the:

  • Eglinton Park Urban Indigenous Community & Mashkiki Gitigaan stewards
  • Toronto Aboriginal Support Services Council
  • Treaty Holders
  • Members of the City’s broader Indigenous community

In this phase of the community engagement process for Phase 1 Implementation: Priority Area 1, the project team worked off of the outcomes of Community Engagement Phase 1 to share design options for community feedback. This feedback will be used to develop a preferred design for the park.

The community engagement activities  in this phase included:

  • Community Advisory Group (CAG) and Indigenous Gardening Advisory Group (IGAG) meetings
  • A public meeting
  • An online survey

The phase outcome was the selection of a preferred design.

July 2023

Online Survey

From July 7 to 23, 2023, an online survey collected feedback on the new skate spot coming to the park as part of the Phase 1 Implementation: Priority Area 1 of the Master Plan.

Download the July 2023 survey summary.

June 2023

Community Advisory Group Meeting 3

On June 6, 2023, the project team met with the CAG to present a project update on Phase 1 of the Eglinton Park Master Plan implementation.

Download the June 2023 CAG meeting summary.

Online Survey

From June 2 to June 18, 2023, an online survey collected thoughts on the preferred designs for the park improvements for Phase 1 of the Master Plan implementation.

Download the June 2023 survey summary.

April 2023

Indigenous and Gardening Advisory Group Meeting 2

On April 26, 2023, the project team met in person with the IGAG to provide an overview of the Eglinton Park Master Plan implementation and complete a site tour that highlighted key Indigenous history in the park.

Download the April 2023 IGAG meeting summary.

March 2023

Community Advisory Group Meeting 2

On March 28, 2023, the project team met with the CAG to review the Eglinton Park Master Plan and components included in Priority Area 1.

Download the March 2023 CAG meeting summary.

Master Plan Revisions

Revisions are made to the 2019 Master Plan to incorporate feedback provided by the CAG at the December 6, 2022 meeting. Some members of the CAG were concerned about the proposed organization of the sports fields in the Master Plan and that the proposed fence around the north ball diamond would reduce the flexibility of the open space.

In response, the project team did a detailed study of different configurations of scaled sports fields and reviewed fence requirements for the ball diamond. The study determined that the existing sports fields should remain and that the 2019 Master Plan should be revised accordingly. This approach maintains the existing permit holders and does not require a fence around the ball diamond outfield, allowing for flexibility of the open space for passive use. The proposed wet plaza in the 2019 Master Plan was identified as not being functional and an issue for park maintenance. The Master Plan has been revised and relocates the wet plaza area where the existing wading pool is located. The design for this area of the park will be determined through community engagement at a future phase of the Master Plan implementation.

Visit the Eglinton Park Master Plan section to see all the new revisions.

In this phase of the community engagement process for Phase 1 Implementation: Priority Area 1, the City will share the preferred design with the community and collect feedback. The project will then move into the detailed design phase, where the design team will finalize the preferred design by working through the technical details and drawings for the construction contractor.

The community engagement activities anticipated in this phase include:

  • An Indigenous Advisory Circle (IAC)
  • An online survey

The anticipated phase outcome includes refining the preferred design.

Download the Phase 3 engagement summary.

September 2024

Online Survey

From August 26 to September 16, an online survey collected feedback on the preferred design for the new skate spot and provided an update on the new basketball court.

February 2024

Indigenous Advisory Circle

On Wednesday, February 21, 2024, from 6 to 8 p.m., the Project Team met with members of the Indigenous Advisory Circle (IAC) for the Eglinton Park Masterplan project to present preferred designs for the Phase 1 Mater Plan, as well as, Indigenous placemaking concepts and design options. Further discussions were held with IAC members to expand on Indigenous placemaking design opportunities for the park.

Download the February 2024 IAC meeting summary.

December 2023

Online Survey

From December 15, 2023 to January 5, 2024, an online survey collected feedback on the design options for the Priority Area 1 improvements to the park and skate spot.

Download the December 2023 survey summary.

This section is organized as follows:

  • Eglinton Park Master Plan (with 2023 revisions)
  • Four Priority Areas
  • Developing the Master Plan

Eglinton Park Master Plan

In 2019, the City completed the Master Plan with the help of a professional design consultant, various internal stakeholders, user groups, and the public. The plan has since been revised to incorporate feedback from the public and Community Advisory Group (CAG) in late 2022/early 2023 during the ongoing community engagement process.

The revisions made to the Master Plan include:

  • Maintaining the existing permitted sport recreation fields
  • A slight shift south for the east/west walkway that connects the Oriole Parkway stairs to the main path
  • Shifting the dogs off-leash area south
  • Relocating the proposed skate spot frontage along Eglinton Avenue West
  • Relocating the wet plaza/water feature to the existing wading pool location

A map showing the Eglinton Park Master Plan with 38 numbered labels showing the location of different features and amenities throughout the park. The park is bordered by Eglinton Avenue West to the south, Edith Drive to the east, Roselawn Avenue to the north, and Oriole Parkway to the west. The south area of the park Master Plan includes a plaza, memorial garden, plantings, water wall feature/artwork, outdoor pool, and basketball court. The centre of the park includes a dog fountain next to the arena, the existing ball diamond, and shade structure. The north side of the park includes an open court with trees, grass, a wide path entrance, a lawn area, a pedestrian bike path with fitness equipment. Additional features are included in the design, as listed in the legend.

  1. Open court with trees
  2. Raised roadbed/shared space
  3. Separated pedestrian and bike path with fitness equipment
  4. Paved nature path with fitness equipment
  5. Existing tennis court/ice rink
  6. Fenced off-leash area
  7. Existing ball diamond
  8. Existing heritage garden
  9. Water play feature
  10. Lawn (two existing mini soccer fields during permitted hours)
  11. Lawn (one standard soccer pitch during permitted hours)
  12. Shade structure
  13. Plaza area
  14. Playground (existing modified paving) with a new sandbox
  15. Sensory gardens
  16. North Toronto Memorial Arena
  17. North Toronto Memorial Community Centre
  18. Memorial Garden
  19. North Toronto Memorial Community Centre
  20. Outdoor pool
  21. Plaza
  22. Skate spot
  23. History themed garden
  24. Grass
  25. Fenced basketball court
  26. Water wall feature/artwork
  27. Fire pit
  28. Dog fountain
  29. Seating overlooking rinks/courts
  30. New plantings
  31. Wide staircase
  32. New stairway with new lighting
  33. Raised planter with existing trees
  34. Park sign
  35. Patio area
  36. Wide path entrance
  37. Existing field house with new tool storage
  38. Fence

Four Priority Areas

The Master Plan identifies four priority areas that will help guide implementation, pending current and future budget availability.

Priority Area 1 (in the process of being implemented)
  • North/south pathway from the North Toronto Community Centre to Roselawn Avenue
  • Dogs off-leash area
  • Skate spot (small skateboarding area)
  • Historic themed gardens
  • Improvements to the existing stairs at Oriole Parkway
Priority Area 2
  • Eglinton forecourts
  • Retaining walls
  • Historic themed gardens
  • Basketball court
  • Park signage
Priority Area 3
  • Roselawn treed forecourt
  • Improved ball diamond
  • Mini soccer fields
  • Berm/natural bleacher
Priority Area 4
  • Seating overlooking existing rinks and courts
  • Shared roadway
  • Café spill-out zone at Community Centre

A map showing Eglinton Park, bordered by Eglinton Avenue West to the south, Edith Drive to the east, Roselawn to the north, and Oriole Parkway to the west showing the four priority areas identified in the Master Plan. Priority area 1, show in pink is located in the centre of the park and connects east to west from Edith Drive to Oriole Parkway. Priority area 2, shown in orange is located towards the lower south section of the park, along Eglinton Avenue West. Priority are 3 is located shown in green is a large section at the north area of the park along Roselawn Avenue spanning the width of the entire width of the park. Priority area 4 is located to the east of the park, along Edith Drive and borders priority area 1 at the centre of the park.

Developing the Master Plan

Developing the Master Plan was an extensive process that involved a professional design consultant, various internal stakeholders, user groups, and the public. Various public meetings took place from 2018 to 2019 to develop the Master Plan.

2019

Master Plan Completed

The Master Plan is completed.

Download the Master Plan summary.

June 2019

Public Meeting: Preferred Plan

On June 24, 2019, the City presented the preferred plan at a public meeting at North Toronto Memorial Community Centre.

Download the June 2019 meeting presentation and preferred plan options.

June 2018

Public Meeting: Master Plan Concept

On June 12, 2018, the City presented the concept plan at Oriole Park Junior Public School.

February 2018

Public Meeting and Workshop

On February 26, 2018, the City conducted a public meeting, which included a workshop, to collect information and feedback from the community to help inform the Master Plan. The meeting was held at the Northern District Toronto Public Library.