Information about specific construction activities, traffic updates and construction notices will be regularly updated on this page.
Gardiner Expressway Deck Replacement – South Half
Dates: 5 a.m. on Monday, July 27 to Spring 2021
Location: Gardiner Expressway between Jarvis and Cherry Streets
Time: Mostly 24/7
Impact
Work Details
Dates: 12:01 a.m. on Monday, May 18, 2020 to Spring 2021
Location: Gardiner Expressway eastbound on-ramp at Jarvis Street
Time: Mostly 24/7
Impact:
Alternative Routes:
During this construction, drivers should consider using alternate routes such as the eastbound Bay Street on-ramp, Lakeshore Boulevard East or the Don Roadway to the Don Valley Parkway.
Work Details:
The section of the Gardiner Expressway between Jarvis and Cherry Streets is nearing the end of its service life and this major work will rehabilitate the eastbound Jarvis Street on-ramp, including replacing the entire deck and steel girders.
*Please note lane closure hours could change depending on COVID-19 situation, however one lane on eastbound Lake Shore Boulevard East will always remain open
Due to the current COVID-19 situation, the City is allowing for longer Lake Shore Boulevard East lane closures to help accelerate construction. Lake Shore Boulevard East will be reduced to one lane in each direction between Parliament and Jarvis Streets: Monday to Friday from 9 a.m. to 4 p.m., Friday to Sunday from 7 p.m. to 7 a.m. and Sunday to Thursday from 8 p.m. to 6 a.m. These lane restrictions are needed so crews can safely remove and replace sections of the concrete expressway deck above. There may also be instances in the off-peak hours where traffic will be paused for 15 minutes so crews can safely perform removal and replacement operations.
F.G. Gardiner Expressway Rehabilitation, Jarvis Street to Cherry Street
Dates: 5 a.m. on Monday, October 14 to July 27, 2020
Location: Gardiner Expressway between Jarvis and Cherry Streets
Time: Mostly 24/7
Using an innovative construction technique called Accelerated Bridge Construction, crews replaced the north half of the expressway deck with pre-fabricated sections that were built off-site in the fabrication yard and transferred into place where existing sections were removed.
Dates: 10 p.m. on October 4, 2019 to April 18, 2020
Location: Westbound Lower Sherbourne / Lower Jarvis Streets off-ramp
Time: Mostly 24/7
The contractor replaced the Lower Sherbourne / Lower Jarvis Streets off-ramp by:
Dates: 10 p.m. on July 15 to September 22, 2019
Location: Gardiner Expressway westbound Yonge-Bay-York streets off-ramp
Time: Mostly 24/7
The contractor rehabilitated the Yonge-Bay-York streets off-ramp by:
Dates: Sunday night to Thursday night, until June 13, 2019
Location: Westbound lanes of Lake Shore Boulevard East from Cherry Street to Jarvis Street
Time: Overnight rolling lane closures from 10 p.m. to 5 a.m.
The contractor completed installing access platforms to support crews in future work phases.
Below is an example of the access platforms that were previously installed on the Gardiner Expressway for work on the West Deck rehabilitation. The lane closures on Lake Shore Boulevard East will allow crews to install similar access platforms on the underside of the Gardiner Expressway from Jarvis Street to Cherry Street.