Transportation Services has led the installation of new sidewalks through the Missing Sidewalk Program since 2002. Transportation Services oversees the consultation and delivery of new sidewalks projects constructed as part of state-of-good repair roadway reconstruction, resurfacing projects and watermain construction being delivered by Engineering and Construction Services, or as standalone projects delivered by Transportation Services.
New sidewalk requests can be sent to newsidewalks@toronto.ca.
Local roads remain the largest gap in the walking network and generate the highest number of requests for new sidewalk installations. Nearly one quarter of all local roads in Toronto, or 800 kilometres, are without a sidewalk. Most local roads have residential land uses, and where sidewalks are missing, pedestrians have no alternative but to walk on the roadway or on unpaved road shoulders. In winter months when roads are icy, pavement width is narrowed by snow, and with daylight hours reduced, the walking conditions are less safe than roadways with sidewalks.
For details about upcoming public consultations and opportunities to provide feedback on new sidewalk installation projects, please see Cycling & Pedestrian Public Consultations.
Recent and upcoming projects include:
Street Name | Year | Project Type | Project Descriptions | Ward | Status |
---|---|---|---|---|---|
Aneta Circle | 2023 | Bundled with parks revitalization project | East side of Aneta Circle from Newton Dr (end of park) to Aneta Circle (end of park) | 18 | Planned |
Austin Terrace | 2024 | Standalone project | South side of Austin Terrance from 7 Austin Terrace [E] to 7 Austin Terrace [W] | 12 | Planned |
Avon Avenue | 2023 | Standalone project | South side of Avon Avenue from Avon Crescent to [50m W] Avon Crescent | 5 | Complete |
Aylesworth Avenue | 2022 | Bundled with local road resurfacing and watermain replacement | East side of Aylesworth Avenue from Lillington Avenue to Haslam Street, where missing | 20 | In progress |
Bales Avenue | 2023 | Standalone project | East side of Bales Avenue from Avondale Avenue to Glendora Avenue | 18 | Planned |
Bartonville Avenue West | 2023 | Standalone project | Bartonville Avenue West from [End] Bartonville Avenue W to Jane Street | 5 | Complete |
Bayview Avenue | 2023 | Standalone project | West side of Bayview Avenue from [285 m N] River Street East Bayview Ramp to River Street East Bayview Ramp | 13 | Planned |
Blaydon Avenue | 2022 | Bundled with local road resurfacing and watermain replacement | North side of Blaydon Avenue from Denbigh Crescent to Whitburn Crescent | 6 | Cancelled |
Bobmar Road | 2020 | Bundled with nearby state-of-good-repair work | West side from Ellesmere Road to 140 metres north of Military Trail | 25 | Complete |
Braywin Drive | 2020 | Standalone project | North side from 36 Braywin Drive to 48 Braywin Drive | 1 | Complete |
Burbank Drive | 2023 | Bundled with local road resurfacing | West side of Burbank Drive from [50m South] of Elmira Court to Blithfield Avenue | 17 | Planned |
Cardell Avenue | 2022 | Bundled with local road resurfacing and watermain replacement | South side of Cardell Avenue from Weston Road to Fairglen Crescent | 5 | Complete |
Carpenter Road | 2023 | Bundled with major road resurfacing and watermain replacement | East side of Carpenter Road from Steeles Avenue West to Bathurst Street | 6 | Planned |
Coldstream Avenue | 2020 | Bundled with local road reconstruction | Coldstream Avenue between Chicoutimi Avenue and Mona Drive | 8 | Cancelled |
Denbigh Crescent | 2022 | Bundled with local road resurfacing and watermain replacement | South side of Denbigh Crescent from Whitburn Crescent to Blaydon Avenue | 6 | Cancelled |
Donalda Crescent | 2021 | Bundled with park revitalization project | West side from existing sidewalk at north end of the park to 70m south | 22 | Complete |
Donino Avenue | 2022 | Bundled with local road reconstruction | West side of Donino Avenue from Mill Street to Donino Avenue bridge | 15 | Complete |
Dunera Avenue | 2023 | Bundled with local road resurfacing |
North side of Dunera Avenue from Payzac Avenue to Galloway Road |
24 | Planned |
Dunlop Park | 2023 | Standalone project |
South side of Dunlop Park from 9 Dunlop Avenue to Dunlop Park Trail |
20 | Planned |
Dwight Avenue | 2021 | Bundled with nearby state-of-good-repair work | West side of Dwight Avenue from Birmingham Street to Maple Boulevard | 3 | Cancelled |
Elder Avenue | 2022 | Bundled with watermain replacement | North side of Elder Avenue from Thirtieth Street to Thirty Second Street | 3 | Complete |
Fairglen Crescent | 2022 | Bundled with local road resurfacing and watermain replacement | South side of Fairglen Crescent from Weston Road to Cardell Avenue | 5 | Complete |
Falaise Road | 2023 | Standalone project | East side of Falaise Road from Kingston Road to Warnsworth Street | 24 | Complete |
Fallingbrook Road | 2023 | Bundled with adjacent local road resurfacing | East side of Fallingbrook Road from Fallingbrook Crescent to Queen Street East | 20 | Planned |
Flint Road | 2023 | Standalone project | West side of Flint Road from Finch Corridor Trail to [200m N] Supertest Road | 6 | In progress |
Honiton Street | 2023 | Bundled with local road resurfacing and watermain replacement | West side of Honiton Street from Kennard Avenue to Cavotti Crescent | 6 | In progress |
Hopewell Avenue | 2022 | Bundled with local road reconstruction | North side of Hopewell Avenue from 105 metres east of Dufferin Street to Walter Saunders Memorial Park Trail | 8 | Complete |
Hotspur Road | 2022 | Bundled with nearby state-of-good-repair work | East side of Hotspur Road from Neptune Drive to existing sidewalk | 8 | Complete |
Hubbard Boulevard | 2023 | Bundled with local road reconstruction | North side of Hubbard Boulevard from Maclean Avenue to Balsam Avenue | 19 | Planned |
Inverness Avenue | 2021 | Bundled with nearby state-of-good-repair work | South side from Islington Avenue to Rothsay Avenue | 3 | Complete |
Lauderdale Drive | 2022 | Bundled with local road resurfacing and watermain replacement | Southwest side of Lauderdale Drive from Rollscourt Drive to Heathcote Avenue | 15 | Cancelled |
Markdale Avenue | 2020 | Bundled with nearby state-of-good-repair work | West side from Strathearn Road to south end of Markdale Avenue | 12 | Completed |
Marine Parade Drive | 2023 | Standalone project | South side of Marine Parade Drive from Marine Parade Drive to Waterfront Drive | 3 | In progress |
Middlefield Road | 2023 | Bundled with major road resurfacing | West side of Middlefield Road from Passmore Avenue to Steeles Avenue | 23 | Planned |
Mildenhall Road | 2021 | Standalone project | East side from Lawrence Avenue East to Blythwood Road | 15 | Complete |
Moore Avenue | 2023 | Standalone project | North side of Moore Avenue from #1213 Bayview Avenue to Sandy Bruce Park | 15 | Planned |
Muircrest Drive | 2023 | Stand-alone project | West side of Muircrest Drive from Broadlands Boulevard to Broadlands Park Trail | 16 | Planned |
North Queen Street | 2022 | Standalone project | Both sides of North Queen Street from The East Mall to Eastside Drive | 3 | In progress |
Orman Avenue | 2022 | Bundled with local road resurfacing | North side of Orman Avenue from Symes Road to Hilldale Road | 5 | In progress |
Panmure Crescent | 2023 | Bundled with local road resurfacing | North side of Panmure Crescent from Bonnechere Crescent to Bonnechere Crescent | 21 | Cancelled |
Parkwood Avenue | 2020 | Standalone project | West side from St. Clair Avenue West to 42 metres north of St. Clair Avenue West | 12 | Complete |
Penetang Crescent | 2023 | Bundled with local road resurfacing |
South and east side of Penetang Crescent from Haileybury Drive to Bonnechere Crescent |
21 | Cancelled |
Ralph Street | 2022 | Standalone project | Connect pedestrian crossing on Ralph Street from Rosemount Avenue to Lawrence Avenue West | 5 | Completed |
Richdale Court | 2022 | Bundled with local road resurfacing and watermain replacement | Both sides of Richdale Court from Longfield Road | 2 | Cancelled |
Silverhill Drive | 2022 | Bundled with local road resurfacing | West side of Silverhill Drive from Billingham Road to north of Lynnford Drive | 3 | Complete |
Sloley Road | 2024 | Bundled with major road reconstruction | North side of Sloley Road from Gradwell Drive to Dorset Road | 20 | Planned |
South Kingslea Drive | 2020 | Bundled with local road reconstruction | South Kingslea Drive between Kingslea Court and Ivy Lea Crescent | 3 | Cancelled |
Strathearn Road | 2021 | Bundled with local road reconstruction | South side of Strathearn Road from Glen Cedar Road to Bathurst Street | 12 | Cancelled |
Superior Avenue | 2022 | Standalone project | Connect end of existing sidewalk to the Great Lakes Park Trail | 3 | Complete |
Symes Road | 2022 | Bundled with local road reconstruction/resurfacing and watermain replacement | North side of Symes Road from Terry Drive to Glen Scarlett Road and East side of Symes Road from Terry Drive to Orman Avenue | 5 | In progress |
Tarragona Boulevard | 2021 | Standalone project | North side from Gunns Road to Park Entrance | 5 | Complete |
The Bridle Path | 2023 | Bundled with local road reconstruction | North side of The Bridle Path from Bayview Avenue to Timberglade | 15 | Planned |
Thorncrest Road | 2022 | Bundled with local road reconstruction | East side of Thorncrest Road from Rathburn Road to Islington Avenue | 2 | Complete |
Torlake Crescent | 2023 | Bundled with local road reconstruction | Both sides of Torlake Crescent from Kipling Avenue to Kipling Avenue | 3 | Planned |
Toynbee Trail | 2023 | Standalone project |
North side of Toynbee Trail from Livingston Road to [200m E] Livingston Road |
24 | Planned |
Westgate Boulevard | 2023 | Bundled with Basement Flooding Protection Program and local road resurfacing | East side of Westgate Boulevard from Delhi Avenue to Armour Boulevard | 6 | Planned |
Windsor Street | 2021 | Standalone project | West side from 50 m south of Newcastle Street to 100 m south of Newcastle Street | 3 | Complete |