Construction of the Gardiner Section 2 from Dufferin Street to Strachan Avenue began in November 2023 and is anticipated to be completed mid-2027.
The F.G. Gardiner Expressway has been in service for more than 60 years and with the effects of weathering, salt and increasing traffic loads, it is approaching the end of its original design life. In order to maintain a safe roadway and ensure a state of good repair, a Strategic Rehabilitation Plan consisting of six complex projects was adopted by Toronto City Council in December 2016. Section 1 construction work was completed in 2021.
The scope of work for Gardiner Section 2 involves replacing 700 metres of concrete deck and girders, rehabilitating the associated substructure and installing new street lighting.
October 2024
Construction Update (Dated: October 17, 2024)
Construction Update (Dated: October 2, 2024)
September 2024
Construction Update (Dated: September 24, 2024)
Construction Update (Dated: September 19, 2024)
August 2024
Construction Update (Dated: August 27, 2024)
Construction Update (Dated: August 2, 2024)
July 2024
Construction Update (Dated: July 26, 2024)
Virtual Public Information Presentation (Dated: July 23, 2024)
Construction Update (Dated: July 16, 2024)
Construction Update (Dated: July 11, 2024)
May 2024
Demolition at Exhibition GO Begins
Jameson On-Ramp to Westbound Gardiner
Demolition and Reconstruction Work Begins
April 2024
March 2024
Virtual Public Information Presentation
February 2024
Construction Start Up Notice (Dated: February 9, 2024)
Work Hours: Construction will take place primarily from 7 a.m. to 11 p.m. Monday to Saturday, with occasional work from 9 a.m. to 5 p.m. on Sundays. Scheduling may vary based on the nature of the work.
Overnight Work: During overnight hours, various activities, including the shifting of traffic barriers between work stages and the delivery of materials, may take place intermittently. When structure work is required over the Exhibition GO Station, overnight construction work will be permitted when the station is not in operation in order to minimize impacts to transit users. During these times, construction impacts and noise levels are expected to be similar to daytime construction activities.
Pedestrian Access: Pedestrian access on Manitoba Drive and through the Exhibition GO Station connecting Atlantic Avenue to Manitoba Drive will be maintained for the duration of the project with intermittent closures as required to allow for overhead work. This will take place during the night when the Exhibition GO Station is not in use, which typically begins half an hour after the last GO Train departs Exhibition GO Station and up to half an hour before the first GO Train arrives at Exhibition Station. During these times, signage will be posted.
A detailed congestion management plan will be used to address the impact of the Gardiner Expressway lane reductions and the other construction taking place downtown. Leveraging the Liberty Village Construction Hub, the plan will include traffic diversion, a coordinated signage plan, the use of traffic agents, automated congestion monitoring, signal timing adjustments, and public transit adjustments.
Motorists are encouraged to plan their travel and consider public transit.
Currently, planned travel impacts beginning in late March 2024 include:
TTC Service Impacts
Metrolinx Service Impacts
Prior to the commencement of demolition activities, extensive preparatory work was required. As the initial demolition will be on the south portion, work had to be completed to safely enable the relocation of traffic to the north side and prepare the structure for demolition. This included:
The City is rehabilitating the Gardiner Expressway between Dufferin Street to Strachan Avenue. Subscribe to receive details of construction activities that may be disruptive.
Type (don’t copy and paste) your email into the box below, check the box next to the e-update description and then click “Subscribe”. You will receive an email with instructions to confirm your request.